Industrial Engineering (BME503) — extracted question text · 70 marks · 3 Hours
Section AAttempt all q u e s t i o n s i n b r i e f . 0 2 x 7 = 1 4
- aDifferentiate between plant location and plant lay out. CO
- bDefine forecasting. CO
- cWhat do you mean by reorder point in inventory model? CO
- dDefine work study. CO
- eWhat is transportation model and where it is used? CO
- fExplain the dummy activity in network diagram. CO
- gDescribe the unbounded solution and no solution conditions with the help of diagram. CO
Section BAttempt any three o f t h e f o l l o w i n g : 0 7 x 3 = 2 1
- cExplain ABC analysis and VED analysis in inventory control with examples. CO3 K3 A project has the following activities: Perform the following: (i) Draw the Activity-on-Arrow (AOA) network diagram (use dummy activity if required). (ii) Identif y the critical path and the total project duration (in days) A firm manufactures two products A and B with a profit ₹4 and ₹ 5 respectively. The products are made by the machines X and Y. Th e available machine time in minutes for the machines X and Y are 2000 and 1500 respectively. The time taken to make the product A by machines X and Y are 5 and 4 minutes and f or the product B are 3 and 4 m inutes respectively. Formulate the LP model for maximization of the profit
Section CAttempt any one p a r t o f t h e f o l l o w i n g : 0 7 x 1 = 0 7
- bWhat do you mean by process planning? What are the steps of pro cess planning? Also explain the Retrival type of process planning. CO
- aWhat is Master Production Scheduling (MPS)? Explain its role in t h e hierarchy of production planning. CO2 K3 If the activities, their dependencies, and durations for a project are given in the table below
- 1Draw the Activity-on-Arrow (AOA) network diagram. Label events (nodes) appropriately
- 2Perform forward and backward pass calculations. Determine for each activity: • Early Start (ES) and Early Finish (EF) • Late Start (LS) and Late Finish (LF) • Total Float (TF)
- 3Identif y all critical path(s) and state the total project duration
- bClassify queuing models using Kendall's notation. Explain the o perating characteristics (like Lq, Wq) of an M/M/1 queue. CO
- aExplain the steps involved in conducting a time study using a s topwatch. How is the standard time calculated? CO
- bExplain the steps involved in wor k measurement. Also explain SI MO chart, How SIMO chart prepared. CO
- bWhat is an unbalanced assignment problem? How is it converted i nto a balanced one? Solve a sample 3x3 assignment problem for minimization. CO
Question text is extracted from the official AKTU question paper PDF above. Check the original PDF for equations, diagrams and complete wording. Extracted: 2026-08-23.
Industrial Engineering — Other Year Papers
AKTU Industrial Engineering PYQs from other sessions
More B.Tech Semester 5 (2025-26) Papers
Other subjects from same semester and session
Machine Design2025-26Essence Of Indian Traditional Knowledge2025-26Cloud Computing2025-26Design And Analysis Of Algorithm2025-26Constitution Of India2025-26Database Management System2025-26I C Engines Fuels Lubrication2025-26Artificial Intelligence2025-26
View all B.Tech Semester 5 2025-26 papers →Syllabus & More PYQs
Paper solve karne se pehle unit-wise syllabus dekh lo