B.TechSemester 72023-24Power Plant EngineeringKME076

Power Plant Engineering (KME076) - AKTU Question Paper 2023-24

B.Tech · Semester 7 · Free PDF Download

This is the official AKTU Power Plant Engineering Previous Year Question Paper for B.Tech Semester 7, academic session 2023-24. Published by Dr. A.P.J. Abdul Kalam Technical University (AKTU/UPTU), Lucknow. Free PDF download — no login required.

Course:B.Tech
Semester:Semester 7
Session:2023-24
University:AKTU / UPTU

Rate this paper

Questions Asked in 2023-24

Power Plant Engineering (KME076) — complete question paper · 100 marks · 3 Hours

Section AAttempt all q u e s t i o n s i n b r i e f .
  • a
    What are conventional and non-conventional power plants? Give examples. 2 1
  • b
    Differentiate between subcriti cal and supercritical boilers. 2 1
  • c
    Define surge tank. What is its function? 2 2
  • d
    Discuss intercooling and rehea ting in a gas turbine power plant. 2 2
  • e
    Explain the working principle of fast breeder reactors. 2 3
  • f
    Define solar thermal collectors. Give examples. 2 3
  • g
    How does a horizontal-axis wind turbine differ from a vertical -axis wind turbine? 2 4
  • h
    What is tidal energy? Name th e essential components of a tidal power plant. 2 4 i. Explain the function of a switchgear. 2 5 j. Discuss peak load and base load power plants. 2 5
Section BAttempt any three o f t h e f o l l o w i n g :
  • a
    Draw the general layout of a modern coal-based thermal power plant. Explain the four main circuits in the steam power plant
  • b
    Classify hydroelectric power plants. Explain the working of a pumped storage type hydropower plant
  • c
    Explain the working of a BWR with the help of a neat sketch. How is it different from
  • d
    Illustrate the working principle of a fuel cell with the hel p of a diagram. Write their applications
  • e
    Discuss various types of tariffs and explain any two of them . 10 5
Section CAttempt any one p a r t o f t h e f o l l o w i n g :
  • a
    In a Rankine cycle, the steam at the inlet to the turbine is sa turated at a pressure of 35 bar and the exhaust pressure is 0.2 bar. Calculate: (i) The pump work, (ii) The turbine work, (iii) The Rankine eff iciency, (iv) The condenser heat flow, (v) The dryness at the end of the expansio n . A s s u m e a s t e a m mass flow rate of 9.5 kg/s
  • b
    Discuss the factors to be considered for site selection of a steam power plant. 10 1
  • a
    Draw the layout of the hydroelectric power plant with the he lp of a diagram. Describe briefly the functions of each component of the plant
  • b
    What are combined cycle power plants? Explain the working of any one of them with neat sketch
  • a
    Discuss the various parts of a nuclear power plant with the help of a neat sketch. Write their advantages and disadvantages
  • b
    Classify concentrating collectors. Discuss the advantages an d disadvantages of concentrating collectors over flat plate collectors
  • a
    Describe the working of a va pour-dominated geothermal system w i t h t h e h e l p o f a schematic sketch. Write the advantages and disadvantages of the geothermal power plants
  • b
    Explain Ocean Thermal Energy Conversion. Compare the working of open-cycle OTEC systems with closed-cycle OTEC systems
  • a
    A generating station has the following daily load cycle: Time (Hours): 0—6 6—10 10—12 12—16 16—20 20—24 Load (MW): 40 50 60 50 70 40 Calculate (i) maximum demand (ii) units generated per day (iii) average load and (iv) load factor and draw the load curve
  • b
    Write short notes on
  • a
    Pollution from thermal power plants and its control
  • b
    Protective electrical equipment in power plants

Question text is extracted from the official AKTU question paper PDF above. Hindi translations are omitted — every question is printed in English in the original paper. Last verified: 2026-08-23.

Repeated Questions — KME076

Questions that appeared in more than one session, found by comparing 4 years of Power Plant Engineering papers (2021-22, 2022-23, 2023-24, 2024-25)

2x

What are conventional and non-conventional power plants? Give examples. 2 1

Appeared in: 2022-23 · 2023-24

Power Plant Engineering — Other Year Papers

AKTU Power Plant Engineering PYQs from other sessions

Syllabus & More PYQs

Paper solve karne se pehle unit-wise syllabus dekh lo