Quantity Estimation And Construction Management (BCE503) — extracted question text · 70 marks · 3 Hours
- aDefine centerline method in quantity estimation
- bList the main advantage of t he centerline method
- cState the key legal aspects of construction contracts
- dDefine detailed specifications
- eDifferentiate between pla nning and scheduling
- fList the types of hoisting equipment
- gDefine Project monitoring
- aCompare the centerline method with the long and short wall m ethod. Highlight the situations where the centerline method is more suitable
- bExplain briefly the procedure of pre-qualification of contra ctors. State its advantages and drawbacks
- cDescribe the phases of a construction project cycle in detai l. Explain the activities and deliverables associated with each phase
- dIllustrate the following: i. Hoisting Equipments ii. Conveying Equipment iii. Hauling Equipments iv. Excavating Equipments
- eExplain various methods of economic comparison used in proje ct cost management
- aDiscuss the various types of e stimates used in building cons truction. How do these estimates differ in purpose and preparation?
- bExplain the main items of work calculated in estimation of buildings
- aIllustrate the information wh ich should customarily appear i n an advertisement for tenders
- bClassify the labour safety and welfare laws? Explain them. 2 K 3
- aDraw a bar chart and compute the total duration of the proje ct from the data given below: Task 1: 6 days Task 2: 3 days Task 3: 7 days Task 4: 2 days Task 5: 4 days Task 1 and 4 will be started together. Task 2 will start after completion of task 3 and task 3 will take place after task 1. Task 5 will be taken up only after completion of task 3
- bClassify float in a network. Explain its significance and ho w it can be calculated in a PERT/CPM network
- aCompare the advantages and disa dvantages of owning construct ion equipment versus hiring it. Disc uss the factors that influence this decision in construction projects
- bExplain various types of Concrete Production Equipment
- aDiscuss the methods for calcu lating the lifecycle cost of co nstruction equipment
- bExplain break even cost analysis with its advantages and lim itations
Question text is extracted from the official AKTU question paper PDF above. Check the original PDF for equations, diagrams and complete wording. Extracted: 2026-08-23.
Quantity Estimation And Construction Management — Other Year Papers
AKTU Quantity Estimation And Construction Management PYQs from other sessions
More B.Tech Semester 5 (2024-25) Papers
Other subjects from same semester and session
Syllabus & More PYQs
Paper solve karne se pehle unit-wise syllabus dekh lo