B.TechSemester 52022-23Quantity Estimation And Construction ManagementKCE503

Quantity Estimation And Construction Management (KCE503) - AKTU Question Paper 2022-23

B.Tech · Semester 5 · Free PDF Download

This is the official AKTU Quantity Estimation And Construction Management Previous Year Question Paper for B.Tech Semester 5, academic session 2022-23. Published by Dr. A.P.J. Abdul Kalam Technical University (AKTU/UPTU), Lucknow. Free PDF download — no login required.

Course:B.Tech
Semester:Semester 5
Session:2022-23
University:AKTU / UPTU

Rate this paper

Questions Asked in 2022-23

Quantity Estimation And Construction Management (KCE503) — complete question paper

Section AAttempt all questions in brief. 2 x 10 = 20
  • a
    What do you understand by schedule of rates?
  • b
    Define long wall estimates
  • c
    What are centre line method?
  • d
    What do you understand by types of specification?
  • e
    What are the requirement of rate analysis?
  • f
    What are project life cycle with example?
  • g
    What are operational cost of equipment?
  • h
    Write two names of hoisting equipment. (i) Why is direct cost important? (j) What are the reasons for time value of money?
Section BAttempt any three o f t h e f o l l o w i n g : 1 0 x 3 = 3 0
  • a
    Write the general rules for measurement of works
  • b
    Analysis of rate of excavation in foundation in ordinary soil i ncluding lift upto 1.5 m and lead upto 30m and including filling , watering, an ramming of excava ted earth and removal and disposal of surplus earth as directed by engineer-in-charge upon a distance of 30 m
  • c
    Draw with the help of mile stone chart work division structure
  • d
    Explain conveying equipment’s with neat sketch
  • e
    Differentiate between depreciation and obsolescence. Write the advantages of break-even chart
Section CAttempt any one part of the following: 10 x 1 = 10
  • a
    Write the classification of sched uling. How can you calculate t he earliest expected time and latest allowable occurrences time in PERT
  • b
    Figure shows the represents the network of a project and durati on of each activity in number of days is given along the res pective activity. Identify all th e paths through the network and find out the critical path and project duration. 4. Attempt any one part of the following: 10 x 1 = 10
  • a
    Estimate the bill of quantity a m asonry platform 6mx5m from the g i v e n d r a w i n g a n d specification (i) Foundation –Lim e c o n c r e t e ( i i 0 M a s o n r y – I s t class brick with lime mortar (iii) Flooring -2.5 cm cement concrete cover over 7.5 cm lime concrete, over wall only 2.5 cm cement concrete (iv) wall finishing –Outside walls are 12 mm cement plastered 1:6
  • b
    Estimate the quantities of brickwo rk and plastering required in a wall 4 m long, 3 m high and 30cm thick . Calculate also the cost if the rate of brick work is Rs.320.00 per cu m and plastering is Rs8.50 per sq m
  • a
    Find the rate analysis laying and consolidation of Stone Macada m – unit 1 cu.m take 100 cu.m, 225 mtr length of 3.7m wide road, 12 mm thick loose layer
  • b
    Write the rules for preparation of Muster roll with labour safety
  • a
    A machine was purchased for Rs. 4,50,000 on Ist January 2004 an d erection and installation work cost Rs. 60,000. It was replaced by a new one on Ist Janua ry 2012. If the scrap value was estimated as Rs. 1,50,000, W hat should be the rate of depre ciation and depreciation fund on 15th April 20008
  • b
    Explain in detail about various types of earth work equipment’s with special purpose usage for each equipment’s
  • a
    Compare direct and indirect cost in the construction project
  • b
    What are two method used in dis counted cash flow? How do you c alculate discounted cash flow model?

Question text is extracted from the official AKTU question paper PDF above. Hindi translations are omitted — every question is printed in English in the original paper. Last verified: 2026-08-23.

Repeated Questions — KCE503

Questions that appeared in more than one session, found by comparing 2 years of Quantity Estimation And Construction Management papers (2022-23, 2023-24)

2x

Define long wall estimates

Appeared in: 2022-23 · 2023-24

2x

What are the requirement of rate analysis?

Appeared in: 2022-23 · 2023-24

Quantity Estimation And Construction Management — Other Year Papers

AKTU Quantity Estimation And Construction Management PYQs from other sessions

Syllabus & More PYQs

Paper solve karne se pehle unit-wise syllabus dekh lo