- aDefine centerline method in quantity estimation
- bList the main advantage of t he centerline method
- cState the key legal aspects of construction contracts
- dDefine detailed specifications
- eDifferentiate between pla nning and scheduling
- fList the types of hoisting equipment
- gDefine Project monitoring
- aCompare the centerline method with the long and short wall m ethod. Highlight the situations where the centerline method is more suitable
- bExplain briefly the procedure of pre-qualification of contra ctors. State its advantages and drawbacks
- cDescribe the phases of a construction project cycle in detai l. Explain the activities and deliverables associated with each phase
- dIllustrate the following: i. Hoisting Equipments ii. Conveying Equipment iii. Hauling Equipments iv. Excavating Equipments
- eExplain various methods of economic comparison used in proje ct cost management
- aDiscuss the various types of e stimates used in building cons truction. How do these estimates differ in purpose and preparation?
- bExplain the main items of work calculated in estimation of buildings
- aIllustrate the information wh ich should customarily appear i n an advertisement for tenders
- bClassify the labour safety and welfare laws? Explain them. 2 K 3
- aDraw a bar chart and compute the total duration of the proje ct from the data given below: Task 1: 6 days Task 2: 3 days Task 3: 7 days Task 4: 2 days Task 5: 4 days Task 1 and 4 will be started together. Task 2 will start after completion of task 3 and task 3 will take place after task 1. Task 5 will be taken up only after completion of task 3
- bClassify float in a network. Explain its significance and ho w it can be calculated in a PERT/CPM network
- aCompare the advantages and disa dvantages of owning construct ion equipment versus hiring it. Disc uss the factors that influence this decision in construction projects
- bExplain various types of Concrete Production Equipment
- aDiscuss the methods for calcu lating the lifecycle cost of co nstruction equipment
- bExplain break even cost analysis with its advantages and lim itations
Question text is extracted from the official AKTU question paper PDF above. Hindi translations are omitted — every question is printed in English in the original paper. Last verified: 2026-08-23.
Quantity Estimation And Construction Management — Other Year Papers
AKTU Quantity Estimation And Construction Management PYQs from other sessions
More B.Tech Semester 5 (2024-25) Papers
Other subjects from same semester and session
Syllabus & More PYQs
Paper solve karne se pehle unit-wise syllabus dekh lo