Software Project Management (KOE068) — complete question paper · 100 marks · 3 Hours

Section AAttempt all q u e s t i o n s i n b r i e f .
  • a
    Define the project with a suitable example. 02
  • b
    Explain different types of projects. 02
  • c
    Explain the limitations of t he waterfall model. 02
  • d
    Explain the parametric mode l for effort estimation. 02
  • e
    Explain the critical path in softw are project development. 02
  • f
    Discuss the structure of the activity node in the activity network. 02
  • g
    Discuss the activitie s under software configuration management. 02
  • h
    Explain the steps to handle the change control process in a software project. 02 i. Explain job enlargement. 02 j. Discuss organizational behavior. 02
Section BAttempt any three o f t h e f o l l o w i n g :
  • a
    Explain why the discounted c ash flow technique provides bett er criteria for project selection than net profit or return on investment
  • b
    Calculate the function point value for a project with the fo llowing information domain characteristics: Number of user inputs = 30 Number of user outputs = 42 Number of user enquiries = 08 Number of files = 07 Number of external interfaces = 06 Assume that all complexity adjustment values are moderate and weighting factors are average given below in the table. Measurement Paramete r Low Avera ge Hi gh
  • 1
    Number of external inputs (EI) 7 10 15
  • 2
    Number of external outputs (EO) 5 7 10
  • 3
    Number of external inquiries (EQ) 3 4 6
  • 4
    Number of internal files (ILF) 4 5 7
  • 5
    Number of external interfaces (EIF) 3 4 6
  • c
    Illustrate project schedu ling with the help of various project schedule activities. 10
  • d
    Discuss Software Config uration Management. 10
  • e
    Explain the Role of organizati onal behavior in Software Project Management. 10
Section CAttempt any one p a r t o f t h e f o l l o w i n g :
  • a
    The large software projec t that you are managing is doing very well. Your latest estimates predict that your team will finish the project at the end of June 2003, three months ahead of schedule and 15% under budget. You now have to make
  • a
    choice about what to do in this situation. You have thought of three options: (i) Finish early in June; release the project team to work on other projects. Give the unused budget back to your boss. (ii) Use the 3 months and the budget to do more testing on the project to try and find any residual errors. (iii) Use the 3 months and the budget to improve the internal and external documentation for the project. Appl y software management principles; which alternative would you choose?
  • b
    The status of cash flow for f our projects is given in the following table. (Negative figures at the end of year 0 represents initial investment). Cash flow for four projects (Figures are end-of-year total in rupees) Year Project 1 Project 2 Project 3 Project 4 Calculate Net Profit (NP), Payback Period (PP), Return on Investment (ROI) and Net Present Value (NPV) based on above table. You may assume discount rate to be as 10%
  • a
    Outline Rapid Application Model for software development. 10
  • b
    Outline Agile methods for software development. 10
  • a
    ln the application of risk man agement to software development projects has been strongly advocated. ln practice, however, managers are often reluctant to apply the techniques. Derive the reasons you might be think for this
  • b
    Consider the following project specifications with estimated activity durations and precedence requirements. Formulate an activity network using activity-on-node network conventions, carry out forward and backward pass and identify the critical paths. Activity Activity Description Durations (weeks) Precedents A Hardware selectio n 8 B S ystem configuration 5 C lnstall hardware 3 A D Data mi gration 4 B E Draft office procedures 4 B F Recruit staff 12 G User trainin g 5 E, F H lnstall and test s ystem 3 C, D
  • a
    Calculate Estimate At Compl etion (EAC) and Variance At Completion (VAC) if both SPI and CPI influence the project work when given variables are  Budget At Completion (BAC) = $22,000  Earned Value (EV) = $13,000  Planned Value (PV) = $14,000  Actual Cost (AC) = $15,000
  • b
    You are managing a project tha t is six months from its execution. You are now reviewing the project status, and you have ascertained that the project is behind schedule. The actual cost of Activity A is ₹ 2,00,000, and Activity B's is ₹ 1,00,000. The planned value of these activities is ₹ 1,80,000 and ₹ 80,000, respectively. The Activity A is 100% complete. However, Activity B is only 75% complete. Calculate the project's schedule performance index and cost performance index on the review date
  • a
    An organization has detected low job satisfaction in the following departments:  the system testing group.  the computer applications help desk.  computer batch input. Design a model so that these jobs be redesigned to give more job satisfaction?
  • b
    Three different mental obst acles to good decision-making were identified in the text: Faulty heuristics, escalation of commitment, and information overload. Formulate steps do you think can be taken to reduce the danger of each of these

Question text is extracted from the official AKTU question paper PDF above. Hindi translations are omitted — every question is printed in English in the original paper. Last verified: 2026-08-23.

Repeated Questions — KOE068

Questions that appeared in more than one session, found by comparing 3 years of Software Project Management papers (2021-22, 2022-23, 2023-24)

3x

Discuss the activitie s under software configuration management. 02

Appeared in: 2021-22 · 2022-23 · 2023-24

2x

Discuss the structure of the activity node in the activity network. 02

Appeared in: 2022-23 · 2023-24

2x

Discuss Software Config uration Management. 10

Appeared in: 2022-23 · 2023-24

2x

Explain the Role of organizati onal behavior in Software Project Management. 10

Appeared in: 2022-23 · 2023-24

2x

The status of cash flow for f our projects is given in the following table. (Negative figures at the end of year 0 represents initial investment). Cash flow for four projects (Figures are end-of-year total in rupees) Year Project 1 Project 2 Project 3 Project 4 Calculate Net Profit (NP), Payback Period (PP), Return on Investment (ROI) and Net Present Value (NPV) based on above table. You may assume discount rate to be as 10%

Appeared in: 2022-23 · 2023-24

2x

Outline Rapid Application Model for software development. 10

Appeared in: 2022-23 · 2023-24

2x

Outline Agile methods for software development. 10

Appeared in: 2022-23 · 2023-24

2x

Calculate Estimate At Compl etion (EAC) and Variance At Completion (VAC) if both SPI and CPI influence the project work when given variables are  Budget At Completion (BAC) = $22,000  Earned Value (EV) = $13,000  Planned Value (PV) = $14,000  Actual Cost (AC) = $15,000

Appeared in: 2022-23 · 2023-24

2x

You are managing a project tha t is six months from its execution. You are now reviewing the project status, and you have ascertained that the project is behind schedule. The actual cost of Activity A is ₹ 2,00,000, and Activity B's is ₹ 1,00,000. The planned value of these activities is ₹ 1,80,000 and ₹ 80,000, respectively. The Activity A is 100% complete. However, Activity B is only 75% complete. Calculate the project's schedule performance index and cost performance index on the review date

Appeared in: 2022-23 · 2023-24