MCASemester 32023-24Software Project ManagementKCA-013

Software Project Management (KCA-013) - AKTU Question Paper 2023-24

MCA · Semester 3 · Free PDF Download

This is the official AKTU Software Project Management Previous Year Question Paper for MCA Semester 3, academic session 2023-24. Published by Dr. A.P.J. Abdul Kalam Technical University (AKTU/UPTU), Lucknow. Free PDF download — no login required.

Course:MCA
Semester:Semester 3
Session:2023-24
University:AKTU / UPTU

Rate this paper

Questions Asked in 2023-24

Software Project Management (KCA-013) — extracted question text · 100 marks · 3 Hours

Section AAttempt all q u e s t i o n s i n b r i e f . 2 x 10 = 20
  • b
    Which factor is decide d the success of a project. 2 1
  • c
    What do you meant by cash flow forecasting? 2 2
  • d
    What do you meant by net profit? 2 2
  • e
    Define motivation? 2 3
  • f
    Define ideal activit y plan? 2 3
  • g
    What are the two factors used to pro gress of project? 2 4
  • h
    Define baseline bud get. 2 4 i. What are the two measures used to enhance job design? 2 5 j. Define Stress. 2 5
Section BAttempt any three o f t h e f o l l o w i n g : 10 x 3 = 30
  • a
    Explain portfolio management of software projects. Discuss w ith examples
  • b
    Explain how project can be eval uated against strategic, tech nical and economic criteria
  • c
    Explain the importance of forward pass in calculating the ea rliest dates with an example
  • d
    Discuss the change control procedures in detail. 10 4
  • e
    Discuss in detail about the or ganizational structures. 10 5
Section CAttempt any one p a r t o f t h e f o l l o w i n g : 10 x 1 = 10
  • a
    What is risk evaluation? Explain the use of decision trees i n risk evaluation
  • b
    What is Management? Explain i n detail, management control. 1 0 1
  • a
    Where are estimates done and explain the problems with over and under estimates
  • b
    Explain COCOMO – II model. 10 2
  • a
    Briefly explain the steps i nvolved in risk planning in proje ct development
  • b
    Explain Network planning mode l. Explain with an example how critical path can be identified in precedence networks
  • a
    Explain Framework for Project Management and control. 10 4
  • b
    Explain the advantages & disadv antages of fixed price contract model. 10 4
  • a
    Give a brief note on health and safety issues. 10 5
  • b
    Explain the importance of wor king together as a team and the various aspects of team development

Question text is extracted from the official AKTU question paper PDF above. Check the original PDF for equations, diagrams and complete wording. Extracted: 2026-08-23.