Software Project Management (KCA013) - AKTU Question Paper 2024-25
MCA · Semester 3 · Free PDF Download
This is the official AKTU Software Project Management Previous Year Question Paper for MCA Semester 3, academic session 2024-25. Published by Dr. A.P.J. Abdul Kalam Technical University (AKTU/UPTU), Lucknow. Free PDF download — no login required.
Rate this paper
Questions Asked in 2024-25
Software Project Management (KCA013) — complete question paper · 100 marks · 3 Hours
- bWhat are the activities covered by SPM?
- cWhat do you meant by cash flow forecasting?
- dWhat do you meant by cost-evaluation techniques?
- eWhat is dangle in an activity network 3 K4,K5
- fWhat is the significance of a Critical Path Method? 3 K4,K5
- gWhat is meant by setting checkpoints?
- hMention the advantages of function point analysis. 4 K6 i. What is masslow’s hierarchy needs? 5 K2,K4 j. Mention the important causes o f stress encountered in projects. 5 K2,K4
- aWhat is the difference between Information systems and embed ded systems?
- bExplain how project can be evaluated against strategic, tech nical and economic criteria
- cExplain various steps involve d & the objectives of activity planning in detail 3 K4,K5
- dWhat are the advantages & dis advantages of fixed price contracts?
- eExplain in detail about decision making. With an example the strength of the team 5 K2,K4
- aDiscuss the cash flows tec hniques in project development
- bExplain in detail, the various issues to be addressed in eva luating the risks 26 before deciding to take up a project
- aExplain Network planning model. Also explain with an example h o w critical path can be identified in precedence networks. 3 K4,K5
- bExplain how to delayed projec ts can be brought back on track
- aDiscuss the Maslow’s hierar chy of needs with an example. 5 K2,K4
- bExplain the various activities to be performed in “Analyzing th e p r o je c t characteristics”
- aExplain in detail, how cost-be nefit evaluation techniques ca n be used to choose the best among competing project proposals
- bWhat are called “Activity on arrow networks”? Explain the ru les and conventions used in drawing Activity on arrow networks. 3 K4,K5
- aExplain Controlling changes to a project requirement
- bWrite short notes on Team Str ucture and Virtual Team in a So ftware Project. 5 K2,K4
Question text is extracted from the official AKTU question paper PDF above. Hindi translations are omitted — every question is printed in English in the original paper. Last verified: 2026-08-23.
Repeated Questions — KCA013
Questions that appeared in more than one session, found by comparing 4 years of Software Project Management papers (2021-22, 2022-23, 2023-24, 2024-25)
Explain how project can be evaluated against strategic, tech nical and economic criteria
Appeared in: 2021-22 · 2023-24 · 2024-25
What do you meant by cash flow forecasting?
Appeared in: 2023-24 · 2024-25
What are the advantages & dis advantages of fixed price contracts?
Appeared in: 2023-24 · 2024-25
Explain Network planning model. Also explain with an example h o w critical path can be identified in precedence networks. 3 K4,K5
Appeared in: 2023-24 · 2024-25
Explain in detail, how cost-be nefit evaluation techniques ca n be used to choose the best among competing project proposals
Appeared in: 2021-22 · 2024-25
Software Project Management — Other Year Papers
AKTU Software Project Management PYQs from other sessions
More MCA Semester 3 (2024-25) Papers
Other subjects from same semester and session